Lucrări de montare a sistemului de irigare din bd. Mircea cel Bătrân zonele 1-5
Information about customer
Fiscal code/IDNO
Address
MD2044, MOLDOVA, mun.Chişinău, mun.Chişinău, bd.Mircea cel Batrin 4/3
Web site
---
The contact person
Purchase data
Date created
7 Nov 2024, 14:50
Date modified
10 Dec 2024, 12:25
Achizitii.md ID
21307927
MTender ID
CPV
45200000-9 - Lucrări de construcţii complete sau parţiale şi lucrări publice
Type of procedure
Open tender
Award criteria
The lowest price
Funding sources
List of lots
Lot nr. 1 - Lucrări de montare a sistemului de irigare din bd. Mircea cel Bătrân zonele 1-5
Budget: 3184933.63 MDL
Active
Documents of the procurement procedure
cs irigare 29 1.docx
Documents history
-
cs irigare 29 1.docx
ID: 1a7d5781-ad78-44a2-9860-060d7b8405f2
Bidding Documents
-
cs irigare 29 1.docx
ID: 1a7d5781-ad78-44a2-9860-060d7b8405f2
Bidding Documents
-
cs irigare 29 1.docx
ID: 1a7d5781-ad78-44a2-9860-060d7b8405f2
Bidding Documents
-
cs irigare 29 1.docx
ID: 1a7d5781-ad78-44a2-9860-060d7b8405f2
Bidding Documents
Bidding Documents
-
10.12.24 12:25
Date:
15 Nov 2024, 19:46
Question's name:
Caiet de sarcini
Question:
In caietul de sarcini, in descrierea mai multor pozitii se regaseste denumirea brandului HUNTER( ex. Controler irigare cu baterii 22V zone Node-400 Hunter; Electrovana D.2*FI/FE PGV-210-B HUNTER ), dar conform articolului 37, (al.6) din Legea 131/2015 este stipulat: Specificațiile tehnice nu vor face referinţă la o anumită marcă comercială sau la un anumit agent economic, la un brevet, o schiţă sau un tip de bunuri, de lucrări şi de servicii, nu vor indica o origine concretă, un producător sau un operator economic concret. În cazul în care nu există un mod suficient de exact de expunere a cerinţelor faţă de achiziţie, iar o astfel de referinţă este inevitabilă, caracteristicile vor include cuvintele „sau echivalentul”. Rugam repectuos sa va conformati cu cerintele legii.
Answer (25 Nov 2024, 11:50):
Caietul de sarcini va fi modificat.
Date:
15 Nov 2024, 20:22
Question's name:
Caiet de sarcini
Question:
In caietul de sarcini, la multe pozitii nu codul lucrarii cu resursele utilizate. Ex.(poz.5 - AcA07A - Montarea in pamint, in exteriorul cladirilor, a tevilor din PVC tip 4(G) sau 3(M), avind diametrul de 25-90 mm - folosim pentru Teava D. 90/PN10 PE100 SDR17 x 5.4 SM EN . Pentru tevi din PE exista AcA52A - Teava din polietilena, pentru conducte de alimentare cu apa montata in sant, cu diametrul de 20, 25, 32, 40, 50, 63 mm. Utilizarea resurselor necorespunzatoare materialelor utilizate, duce la calcularea incorecta a costului proiectului. Spuneti daca proiectul de executie si devizul de cheltuieli, in baza caror a fost elaborat caietul de sarcini pentru aceasta procedura de achizitie a trecut etapele de verificare si expertizare necesare. Daca da, atunci rugam sa publicati avizul de verivicare
Answer (25 Nov 2024, 11:51):
Caietul de sarcini va fi modificat.
Date:
15 Nov 2024, 20:43
Question's name:
Specificatii tehnice
Question:
In caietul de sarcini , la compartimentul UTILAJ gasim - Controler irigare cu baterii 22V zone Node-400 Hunter . Nu exista in realitate baterii de 22V. Daca este gresit, rugam sa corectati.
Answer (25 Nov 2024, 11:51):
Caietul de sarcini va fi modificat.
Date:
15 Nov 2024, 21:09
Question's name:
Caiet de sarcini
Question:
In caietul de sarcini la toate compartimentele Executarea caminului de vizitare - avem executarea unui singur camin , la care avem 17 capace din fonta. Cum se explica aceasta?
Answer (25 Nov 2024, 11:51):
Caietul de sarcini va fi modificat.
Date:
16 Nov 2024, 19:23
Question's name:
tremen de executare a lucrarilor
Question:
Luind in consideratie termenul de executare a lucrarilor destul de restrins, Va rugam sa ne spuneti daca dispuneti de toate actele permisive de incepere a lucrarilor coordonate cu serviciile necesare(Spatii verzi, Regia Mobilitate Urbana, Apa-Canal, Inspectoratul National de Securitate Publica s.a.)
Answer (25 Nov 2024, 11:52):
Caietul de sarcini va fi modificat.
Date:
25 Nov 2024, 21:49
Question's name:
Caiet de sarcini
Question:
Rugam sa specificati de care Duza pentru pop-up S020 se cer de folosit. Ele exista de tip Spray si de tip Rotator, iar diferenta de pret intre ele este considerabila
Answer (28 Nov 2024, 11:49):
spray daca cautam datele tehnice ale acestui POP UN soro vedem toate caracteristicile.
Date:
25 Nov 2024, 21:51
Question's name:
Caietul de sarcini
Question:
Spuneti daca proiectul de executie si devizul de cheltuieli, in baza caror a fost elaborat caietul de sarcini pentru aceasta procedura de achizitie a trecut etapele de verificare si expertizare necesare. Daca da, atunci rugam sa publicati avizul de verivicare
Answer (28 Nov 2024, 11:50):
Proiectul de executie este in proces de coordonare intre timp vor fi coordonate.
Date:
25 Nov 2024, 21:54
Question's name:
tremen de executare a lucrarilor
Question:
Luind in consideratie termenul de executare a lucrarilor destul de restrins, Va rugam sa ne spuneti daca dispuneti de toate actele permisive de incepere a lucrarilor coordonate cu serviciile necesare(Spatii verzi, Regia Mobilitate Urbana, Apa-Canal, Inspectoratul National de Securitate Publica s.a.). Va rugam totusi sa raspundeti la aceasta intrebare
Answer (28 Nov 2024, 11:46):
Proiectul de executiea este in proces de coordonare intre timp vor fi coordonate.
Date:
25 Nov 2024, 22:13
Question's name:
caiet de sarcini
Question:
Explicati Va rog, in cazul care avem Controler cu baterii, de ce este nevoie de fir electric 2x0,5 mm?
Answer (28 Nov 2024, 11:48):
Avem nevoie de fir pentru conectarea electrovene cu controler
Date:
25 Nov 2024, 22:28
Question's name:
Deviz
Question:
In Deviz-oferta № 6-1-2(Irigarea terenului pe bd. M. Cel Batrin or. Chisinau, bd. Mircea Cel Batrin, 21 - Igor Vieru), la poz. 48 avem Controler irigare cu baterii 22V 4 zone Node-400 Hunter sau analogic - 3 buc, la poz 49 - Controler irigare cu baterii 22V 6 zone Node-600 Hunter sau analogic - 2 buc. Cu aceste controlere, putem conecta 24 electrovane. In deviz avem doar 8 electrovane. Pentru conectarea a 8 electrovane sunt destule 2 buc controlere cu 4 zone, sau 4 controlere cu 2 zone, ce ar fi cu mult mai ieftin. L afel in toate devizele avem surplus de cutii pentru electrovane. Cum se explica acest surplus?
Answer (5 Dec 2024, 12:08):
caietul de sarcini a fost modificat
Date:
6 Dec 2024, 12:19
Question's name:
Termen de executare a lucrarilor
Question:
Luind in consideratie termenul de executare a lucrarilor destul de restrins, Va rugam sa ne spuneti daca dispuneti de toate actele permisive de incepere a lucrarilor coordonate cu serviciile necesare(Spatii verzi, Regia Mobilitate Urbana, Apa-Canal, Inspectoratul National de Securitate Publica s.a.)
In Raspunsul din 25.11.24 ati raspuns ca se va modifica caietul de sarcini. Dar intrebarea a fost despre actele permisive. Luain in consideratie ca fara actele permisive indicate mai sus, care sunt parte obligatorie a proiectului, nu pot fi incepute lucrarile. In cazul lipsei actelor permisive, serviciile(organizatiile) pot stopa lucrarile in orice moment. Va rugam sa ne spuneti concret cu care servicii(Spatii Verzi, Apa-Canal,Termoelectrica, Lumteh, Regia Mobilitate Urbana, Inspectoratul National de Securitate Publica), este coordonat proiectul, si de tineti actele permisive pentru indeplinirea lucrarilor.
Answer (6 Dec 2024, 12:22):
Actele sunt expediate spre coordonare
Date:
6 Dec 2024, 13:14
Question's name:
Termeni de executare lucrari
Question:
Daca actele sunt expediate spre coordonare, reese ca ati pubilcat un anut de achizitii cu un proiect si deviz care nu a trecut procedura de verificare si fara coordonarile necesare. Explicati Va rugam, cum se vor executa lucrarile in 15 zile de la semnarea contractului, daca nu exista actele permisive obligatorii pentru inceperea lucrarilor.
Answer (9 Dec 2024, 12:58):
avizurile necesare sunt obtinute si nu vor incurca la realizarea lucrarilor
Date:
6 Dec 2024, 17:42
Question's name:
Caiet de sarcini
Question:
Va rugam sa ne explicati cum se vor monta Sensorii de ploaie. Numarul sensorilor este egal cu numarul controlerelor, prin urmare sensorii se vor monta langa fiecare boxa pentru elecrtovana. De obicei sensorii se monteaza pe stalpi, or acesti stilpi nu se regasesc in caietul de sarcini.
Answer (9 Dec 2024, 12:57):
În preajma la fiecare boxa pentru electrovana este de ce prinde senzosul.nu este nevoie de stilpi suplimentar, este calculat si cablu pentru a putea deplasa senzorul
Date:
10 Dec 2024, 12:18
Question's name:
Caiet de sarcini
Question:
Pe data de 5.12.24 ati modificat caietul de sarcini, unde suma nu corespunde cu cea din anuntul de participare. Va rugam sa modificati anuntul de participare
Answer (10 Dec 2024, 12:31):
Caietul de sarcini a fost modificat
Date:
10 Dec 2024, 12:26
Question's name:
Valabilitate contract
Question:
In anuntul de participare este indicat termenul de valabilitate a contractului 31 decembrie 2024. Deoarece achizitia va avea loc pe 21.12.2024, nu se incadreaza in termenii indicati. Va rugam sa anulati procedura de achizii, si sa anuntati alta procedura cu respectarea tuturor termenilor si cerintelor stabilite in legislatie.
Answer (11 Dec 2024, 08:12):
Vă rugăm să vă conformați cerințelor impuse de către autoritatea contractantă
Date:
11 Dec 2024, 12:47
Question's name:
Anunt de participare
Question:
Spuneti Va rugam, cu care cerinte trebuie sa ne conformam? Licitatia va avea loc pe data de 22.12.24, executarea lucrarilor in termen de 15 zile, valabilitatea contractului este pana la 31.12.24. Reesind din asta, nici decum nu ne incadram in termenii stabiliti de D-stra. Chiar daca respectam cei mai restrisi termeni de semnare a contractului, depasim termenul de valabilitate a contractului pina la 31.12.24, indicat
de D-stra in anuntul de participare. Suntem intr-o situatie icerta.
Date:
11 Dec 2024, 12:49
Question's name:
Caiet de sarcini
Question:
D-stra afirmati ca proiectul si devizul a trecut etapele de expertiza si verivicare. Dar caietul de sarcini in cadrul procedurii de achizitie actuale, a fost deja modificat de trei ori, si oricum in caietul de sarcini exista inca greseli. Intr-un priect si deviz expertizat si verificat nu pot exista atitea greseli. Din aceasta cauza apar dubii rezonabile ca devizul de cheltuieli nu a fost verificat si expertizat. Va rugam sa publicati avizul de verificare.