Status
Evaluation
Estimated value without VAT
1 073 647,70 MDL
Period of clarifications:
17 May 2021, 15:05 - 23 May 2021, 15:58
Submission of proposals:
23 May 2021, 15:58 - 27 May 2021, 15:58
Supplier technical support:
(+373) 79999801
Subscribe impossible
during the period Evaluation
Lucrări de finisare a construcţiilor
Information about customer
Fiscal code/IDNO
Address
MD-2070, MOLDOVA, mun.Chişinău, locality, str. Valea Radiului, 16
Web site
---
The contact person
Purchase data
Date created
17 May 2021, 14:32
Date modified
21 May 2021, 15:58
Achizitii.md ID
21039693
MTender ID
CPV
45400000-1 - Lucrări de finisare a construcţiilor
Type of procedure
Request price offers (works)
Award criteria
The lowest price
Funding sources
List of lots
Documents of the procurement procedure
anunt_de_participare_reparatii_2021.semnat (1)
Technical Specifications
Anunt corectat
17.05.21 15:12
Caiet de sarcini corectat cu 3 m grund
Technical Specifications
Caiet de sarcini corectat
21.05.21 15:58
Caiet de sarcini corectat cu 3 m grund.semnat
Technical Specifications
Cairt de sarcini corectat
21.05.21 15:58
Date:
17 May 2021, 20:43
Question's name:
Termenul de executare
Question:
In Anunțul de participare găsim 2 termeni de executare: - 16 săptămini, ce constituie 4 luni și - 2 luni. Anunțați termenul corect.
Answer (18 May 2021, 14:01):
Termenul de executare a lucrarilor este stabilit in FDA, si constitue 2 luni. Termenul de 16 saptamini este o greseala mecanica
Date:
17 May 2021, 20:49
Question's name:
Cheltuieli suplimentare
Question:
Explicați, Vă rog, sintagma: ”Cheltuielile suplimentare, aparute ca urmare a maririi volumului lucrărilor fata
de cele incluse în sarcina de lucru, dar care nu au fost luate în consideraţie de ofertant la prezentarea preţului, nu se acoperă de către Beneficiar”. Adică, dacă apare o lucrare necesară, dar care a fost omisă de către devizier, ea nu se executăб chiar dacă va rămîne un perete nefinisat sau se va încălca tehnologia de executare a lucrării? Benefeciarul, în acest caz, nu va avea pretenții față de executant?
Answer (18 May 2021, 14:00):
Nu merge vorba despre o lucrare necesară, dar care a fost omisă de către devizier!!!
Se are in vedere ca daca la momentul demontarii, sau a ator lucrari preventive apar la iveala niste lucruri care necesita lucrari in plus pentru a executa sarcina de baza-tencuiala din cauza crapaturilor, se va strica ceva mai mult decat necesar, etc. aceste lucrari vor fi! executate, dar fara a majora valoarea contractului.
Ceea ce nu presupune nicicum o executare proasta a lucrarilor. Daca aveti un sef de santier care isi poate permite de a încălca tehnologia de executare a lucrării, va rugam sa va abtineti de a participa la licitatie
Date:
20 May 2021, 11:45
Question's name:
Caiet de sarcini
Question:
Buna ziua precizati va rog grosimea, culoarea si modelul de pavaj solicitat (poz. 43)
Answer (21 May 2021, 15:00):
Pavaj vibropresat 100*200*40mm. Culoarea gri.
Date:
20 May 2021, 11:45
Question's name:
Caiet de sarcini
Question:
precizati va rog dimensiunile si culoarea borduri (poz. 44)
Answer (21 May 2021, 15:01):
Bordura 1000*200*80mm (lungime,lăţime,grosime). Bordura tot din categoria vibropresat. Culoarea gri.
Date:
20 May 2021, 11:50
Question's name:
Garantie pentru oferta
Question:
publicati va rog rechizitele bancare in vederea perfectarii garantiei pentru oferta, multumim anticipat
Answer (20 May 2021, 16:05):
Cititi atent. s-a solicitat scrisoare de garantie bancara
Date:
20 May 2021, 21:03
Question's name:
C
Question:
”Daca aveti un sef de santier care isi poate permite de a încălca tehnologia de executare a lucrării, va rugam sa va abtineti de a participa la licitatie”, MULTUMESC pentru sfat, dar am rămas dezamăgiți de răspunsul Dumneavoastră. Răspunsul ar trebui să fie scurt, clar si la subiect..... Însă, așa și nu ați răspuns la întrebarea mea: De ce OE ar trebui să execute gratis unele lucrări, ”se va strica ceva mai mult decat necesar, etc. aceste lucrari vor fi! executate, dar fara a majora valoarea contractului.”? Deducem că aveți o interpretare greșită precum că OE este o Organizație de binefacere.
Answer (21 May 2021, 15:05):
Deducerea dvs a fost inteleasa
Date:
20 May 2021, 21:06
Question's name:
C1
Question:
Cu privire la postarea precedentă, se cere sintagma - CITIȚI ATENT întrebarea mea.
Answer (21 May 2021, 15:55):
Concret si la tema va rog. Care este inrebarea?
Date:
21 May 2021, 11:58
Question's name:
Caiet de sarcini
Question:
Cititi atent. poz. 30 Aplicarea manuala a grundului cu cuart "Betonocontact" . . . = 22.14m2 dar poz. 31 Pardoseli din placi de gresieportelanata . . . = 25.53 m2, deci prin urmare cum se face grunduim 22.14m2 dar placam 25.53m2, diferenta de 3.39 m2 cine o achita? Cheltuielile suplimentare nu acceptati si nici nu prevedeti toata cantitatea necesara in caietul de sarcini, totodata doriti lucrari de calitate, tinem sa mentionam faptul ca Caietul de sarcini trebuie sa contina toate lucrarile necesare de indeplinit, iar cele care nu sunt prevazute nu pot fi executate
Answer (21 May 2021, 15:04):
Am inteles atentionarea dvs.
Only authorized platform users may ask questions during the clarification period.